Production routing is the process of planning and organising the sequence of operations required during a particular production process.
It must take into account
- Tools and workstations
- Setup time
- Run time
- Maintenance time
- Labour
- Process control
- Concurrency
- Inspection gates
[1]
Example
Production of 250 boxes of biscuits
Routing for 250 biscuit boxes
| Op |
Work centre |
Setup (h) |
Run (h/unit) |
Run for 250 boxes (h) |
Queue + move (h) |
Op elapsed (h)
|
| 10 |
Weigh and mix |
0.40 |
0.006 |
1.50 |
3 |
4.90
|
| 20 |
Sheet and cut |
0.75 |
0.010 |
2.50 |
4 |
7.25
|
| 30 |
Bake |
1.00 |
0.020 |
5.00 |
6 |
12.00
|
| 40 |
Cool |
0 |
0.012 |
3.00 |
5 |
8.00
|
| 50 |
Decorate |
0.50 |
0.008 |
2.00 |
4 |
6.50
|
| 60 |
Pack |
0.30 |
0.005 |
1.25 |
3 |
4.55
|
| Total |
|
2.95 |
|
15.25 |
25 |
43.20
|
For operation $i$,
$$
t_{\text{run},i}^{(Q)}=Q t_{\text{run},i},
$$
and
$$
t_{\text{elapsed},i}=t_{\text{setup},i}+t_{\text{run},i}^{(Q)}+t_{\text{queue+move},i}.
$$
Total tallies:
$$
T_{\text{touch}}=\sum_i\left(t_{\text{setup},i}+t_{\text{run},i}^{(Q)}\right)=2.95+15.25=18.20\ \text{h},
$$
$$
T_{\text{elapsed}}=\sum_i t_{\text{elapsed},i}=43.20\ \text{h}.
$$
The difference is waiting time:
$$
T_{\text{wait}}=T_{\text{elapsed}}-T_{\text{touch}}=43.20-18.20=25.00\ \text{h}.
$$
Thus
$$\begin{gathered}
\frac{T_{\text{touch}}}{T_{\text{elapsed}}}
=42.1\%, \\
\frac{T_{\text{wait}}}{T_{\text{elapsed}}}
=57.9\%,
\end{gathered}$$
so touch time is just over two fifths of the span (42.1%), while waiting time accounts for nearly three fifth.
A scheduler that considers only touch time will promise an extremely unrealistic delivery date.
Contingency
In addition to an optimised standard routing, it is often desirable to create alternative routings as backup, in case a particular machine/raw material is unavailable.
When subcontractors are hired, the planning concerning their work is known as phantom planning, in which the general rule is to leave a generous time buffer for unexpected delays.