Metra Potential Method (MPM)
Appearance
Image: Rong Martin-Siebler ZHOU and RonzzWikiCowriter AI · CC BY-SA 4.0
First developped by Bernard Roy et al.,[1] Metra Potential Method (MPM) is a method for organising different tasks ($J_j$) in a scheduling problem by
- analysing the dependency of each tasks ($J_{jx},J_{jy} \dots \to J_{jz}$)
- Identify thereby the theoretical earliest start time for each task ($t_i(j)$)
- Identify the final due time ($T^*$)
- Calculate backwards the latest start time for each task for respecting the due time ($t^*_i(j)$).
Slack
Slack is additional time available (for unexpected delays, etc.) without impacting performance on specific criteria.
Total slack
$$ \text{Total slack}=t^*_i(j)-t^_i(j) $$
which measures the available slack for task $J_j$ without impacting overall finish time, given there is no other delay elsewhere.
Free slack
$$ \text{Free slack}=t_i(j+1)-t_f(j) $$
which measures the available slack for task $J_j$ without impacting the start time of tasks that depend on it.
In general,
$$ \text{Free slack} \le \text{Total slack} $$