Metra Potential Method (MPM)

From Wikibase
Revision as of 13:37, 13 November 2026 by Rongzhou (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Languages: English · français · Esperanto

An example graphical representation of MPM
Image: Rong Martin-Siebler ZHOU and RonzzWikiCowriter AI · CC BY-SA 4.0
· Open in a new tab

First developped by Bernard Roy et al.,[1] Metra Potential Method (MPM) is a method for organising different tasks ($J_j$) in a scheduling problem by

  • analysing the dependency of each tasks ($J_{jx},J_{jy} \dots \to J_{jz}$)
  • Identify thereby the theoretical earliest start time for each task ($t_i(j)$)
  • Identify the final due time ($T^*$)
  • Calculate backwards the latest start time for each task for respecting the due time ($t^*_i(j)$).

Slack

Slack is additional time available (for unexpected delays, etc.) without impacting performance on specific criteria.

Total slack

$$ \text{Total slack}=t^*_i(j)-t_i(j) $$

which measures the available slack for task $J_j$ without impacting overall finish time, given there is no other delay elsewhere.

Free slack

$$ \text{Free slack}=t_i(j+1)-t_f(j) $$

which measures the available slack for task $J_j$ without impacting the start time of tasks that depend on it.

In general,

$$ \text{Free slack} \le \text{Total slack} $$